Project 1 Tamworth Neighbourhood

'Decanting' and demolition of the 'bird blocks'

The decision was taken in 2010 that the blocks will be emptied and demolished one at a time, in a phased approach. Residents within these blocks have therefore been moved to alternative accommodation following the same phased approach. This process is known as decanting. This 'decanting' process started in 2010 and to date over 250 household have been successfully rehoused in homes that meet their individual needs. This means that 3 of the 4 tower blocks are now empty and the Decant Officer is working with residents in the remaining tower block, Falcon Court. Residents within this block will be moving this year and we hope to have found new homes for all households by September 2013.

If you live in this block and would like more information please contact Julia Burke on 0300 777 7777 or Julia.burke@traffordhousingtrust.co.uk  

If you would like to see a copy of the decant policy please click here

The demolition

As many of you will have seen the physical demolition work has now started. Robinson and Birdsell Ltd have been appointed to demolish Osprey and Raven Courts, along with two buildings owned by Trafford Council, the CCTV hub and the shops.

Work started on 15th October 2012 and is due to be completed by April 2013. Work is progressing well and both Osprey and Raven Courts have been demolished. The contractor is in the process of 'crusting' and removing material from site.

In order to carry out demolition at Eagle Court it will be necessary to close Dudley Close. This will take place from 8th April 2013. Car parking will be available on the former car park for the shops.

Tamworth Towers Update

Firstly I would like to thank all our customers at Tamworth for their on-going patience during the works; work has been on-going for a number of months and residents have been very patient throughout the process.

Hopefully residents are now starting to see and feel the benefits of the work. The external works to these blocks has now officially been completed (with the exception of a few snags) and residents should now be benefitting from much warmer homes and cheaper bills. The external work has also made a massive difference to how the blocks look - as you can see from the pictures below.

 Tamworth picsTamworth pics3

During this time residents within the blocks have also been provided with new kitchens and bathrooms and therefore has benefitted from improvements inside and outside of their homes. If you live in one of these blocks and would like to give some feedback please email Corinna.Dale@traffordhousingtrust.co.uk

The Trust has also been working with Action for Sustainable Living to ensure that residents are making the most of the new technologies. This project is part of a 'Count Us In' pilot which aims to evaluate the importance of tenant engagement and education when retrofitting. For more information have a look at the most recent report by clicking here.

You can also obtain more information from the National Housing Federation website http://www.housing.org.uk/policy/greener_neighbourhoods/count_us_in.aspx

The work that the Trust has been doing with Action for Sustainable Living has been recognised and we have been shortlisted for a Green Build Award. More information can be obtained by following the link below: http://www.greenbuildnews.co.uk/news-details/Greenbuild-Awards-2013-finalists-revealed/780

And we haven't finished yet….

There are still a few things that need doing to finish off the blocks, including communal areas and lifts and residents can see a timetable below for when we are hoping to carry out these works:

Clifford Court - lift replacement due to commence May 2013

Clifford Court - communal work including painting and replacement communal and flat doors has started and is due to complete by April 2013

Grafton Court and Pickford Courts - communal work including painting and replacement communal and flat doors is due to commence after April 2013

The above dates are indicative and may change so please continue to check this website for further updates.

If you would like any further information regarding anything above please email Alexandra.Atkinson@traffordhousingtrust.co.uk

 

 

Links to further information on current Masterplan projects ...

Masterplan Interactive Map    Project 1      Project 3      Project 7      Employment & Training      Events & Getting Involved 

Social Media title button

Click on the icons to go to our social media.

Facebook icon 40x40    Twitter Icon 40x40    blog roundel 40X40     YouTube Icon 4x40    Linked In Icon 40x40

Getting Involved
Skills 4 you button

Contact Us

Email here or call on 0300 777 7777

© Trafford Housing Trust Limited.

Registered in England and Wales Reg No 04831118. Registered Office: 126 - 150 Sale Point, Washway Road, Sale, Manchester, M33 6AG.
Charity Reg No 1106967; Housing Corporation No L4440; VAT No 854 7727 85.

Accreditations